Construction site update L190
/ News
The work is progressing rapidly!
The entire underpass, including the drag plates, has been concreted, sealed, and already backfilled.
Around 100 m of DN 800 concrete sewer pipe has been successfully laid and connected to the existing system.
Approximately 130 m of kerbstones have been laid and the asphalting work is in full swing.
Construction phase 3 is just around the corner:
Traffic will then no longer be diverted via the bypass, but will instead be routed directly over the new asphalt surface.