Progress at our ARGE Getzner construction site in Bludenz

/ Media library / News / Press Release

In calendar week 13, we celebrated an important milestone: The first precast columns, standing an impressive 18 meters tall, were successfully installed! The columns are equipped with brackets and supports and will eventually support three levels: the first floor, the second floor, and the roof.

The scale of this project is also evident in the amount of materials used: Approximately 9,000 m³ of concrete and about 1,300 metric tons of reinforcing steel have already been installed—a remarkable achievement by our entire team!

A big thank you to the construction site workers and the dedicated foremen: Christian Brand (Jägerbau), Mariano Saler (Nägele), Markus Krenn (TOGA)
Their dedication is what makes this progress possible!

On Friday, March 20, 2026, the final floor slab was also successfully poured—another major step toward completing the structural shell.
We’re pleased with how smoothly things have gone and are looking forward to the next phases of construction with great enthusiasm! 