ARGE A14 INSB Klaus – Work is right on schedule!

/ News / Press Release

Since starting on March 24, 2025, renovation work on the ARGE A14 INSB Klaus construction section of the A14 Rheintal/Walgau motorway has been proceeding according to plan—and even slightly faster than expected!

In the section between km 31.800 and km 32.630, road surfaces, drainage systems, and bridges are being comprehensively renovated in three construction phases. Construction phase 1 is currently being implemented at full speed and with full commitment.

 

From today's perspective, we are about two weeks ahead of schedule. The planned transition to construction phase 2 can therefore take place on June 16, 2025, at the latest – maybe even earlier!

 

A big thank you to everyone involved for their dedicated work!