Getzner Construction Site Update

/ News / Press Release

Work is proceeding according to schedule at our Getzner construction site, which we are carrying out as a joint venture with other construction companies.

The ceiling above the ground floor is already complete, as is the first half of the first floor. Starting in the middle of calendar week 34, the next beams and ceiling slabs will be installed, and construction will continue to move forward.

Currently, around 40 employees are working on the construction site. To date, an impressive 14,000 m³ of concrete has already been poured.

A big thank you to everyone involved for their dedication and excellent teamwork!

Foremen:
Mariano Saler (Nägele Hoch- und Tiefbau)
Christian Brandl (Jägerbau)
Markus Krenn (Tomaselli Gabriel Bau)